Damji Shamji Zenith, Ghatkopar West

by Chandrakant And Co · Ghatkopar West, Mumbai 400086 · Map

Launched
Mar 20252 yrs 9 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
58%Mid-construction
Booked
37 of 6161% · 7 in Jul 2026
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
61
Total units
61
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)58%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 8%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 58%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 58%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%58%0%37
100%50%0%7
100%8%0%7

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Damji Shamji Zenith by Chandrakant And Co is a 61-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in March 2025 with possession due in December 2027. 37 units booked out of total 61 units. The concrete structure (RCC) is 58% complete.

Read full summary

Damji Shamji Zenith is a BMC-sanctioned project by Chandrakant And Co in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800079590. It was launched in March 2025. It has 61 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 58% complete, final finishes not started.

37 units booked out of total 61 units (61%). Since the July 2026 update, 30 more units have been booked and the reported concrete structure (RCC) has gone from 50% to 58%.