Building No. 3 Of Cts No. 64-A5 Manas Apartment, Powai

by Silvester Builders & Developers · Powai, Mumbai 400076 · Map

Launched
Mar 20252 yrs 9 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
25%Mid-construction
Booked
1 of 186%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
9
2 BHK
9
Total units
18
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)25%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 25%Jul 2026: Concrete structure (RCC) 25%Oct 2026: Concrete structure (RCC) 25%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 25%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%25%0%1
100%25%0%1
100%25%0%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Building No. 3 Of Cts No. 64-A5 Manas Apartment by Silvester Builders & Developers is an 18-unit BMC-sanctioned project in Powai, Mumbai 400076, launched in March 2025 with possession due in December 2027. 1 unit booked out of total 18 units. The concrete structure (RCC) is 25% complete.

Read full summary

Building No. 3 Of Cts No. 64-A5 Manas Apartment is a BMC-sanctioned project by Silvester Builders & Developers in Powai, Mumbai 400076, registered with MahaRERA as P51800079642. It was launched in March 2025. It has 18 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 25% complete, final finishes not started.

1 unit booked out of total 18 units (6%).