Skip to main content

Dynamix 36, Borivali West

by Nakasha Dynamix LLP · Borivali West, Mumbai 400103 · Map

Launched
Mar 20253 yrs 3 mths promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services7%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 7%Excavation 100%Concrete structure (RCC) 100%Final finishes 7%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%7%–
100%60%0%–
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Dynamix 36 by Nakasha Dynamix LLP is a BMC-sanctioned project in Borivali West, Mumbai 400103, launched in March 2025 with possession due in June 2028. The concrete structure (RCC) is complete.

Read full summary

Dynamix 36 is a BMC-sanctioned project by Nakasha Dynamix LLP in Borivali West, Mumbai 400103, registered with MahaRERA as P51800079656. It was launched in March 2025. Its MahaRERA status is Active.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 7% complete.

Since the July 2026 update, the reported concrete structure (RCC) has gone from 60% to 100%.