Ranbir Green Path, Goregaon East

by Green Developers LLP · Goregaon East, Mumbai 400063 · Map

Launched
Mar 2025First of 2 phases
Possession (MahaRERA)
Jan 2029Not extended
Concrete structure
88%Weighted across 2 phases
Booked
142 of 15691%
Buildings
20.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
131
Other units
25
Total units
156
Buildings
2
Land
0.9 acres
Phases
2
MahaRERA complaints
0
Reserved units
139

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Ranbir Green Path E
Mid-construction
P51800079703020%25%
Ranbir Green Path A, B And C
Mid-construction
P5180008075913192%95%
Show updates by phase

Ranbir Green Path E (P51800079703)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%20%0%2
100%20%0%2
100%0%0%0

"–" means MahaRERA shows no figure for that update.

Ranbir Green Path A, B And C (P51800080759)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%92%10%140
100%92%10%140
100%17%0%140

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)88%
Finishes, lifts and services9%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 16%Jul 2026: Concrete structure (RCC) 88%Oct 2026: Concrete structure (RCC) 88%Dec 2025: Final finishes 0%Jul 2026: Final finishes 9%Oct 2026: Final finishes 9%Excavation 100%Concrete structure (RCC) 88%Final finishes 9%

How to read construction stages

Compared with 6 similar projects in PIN 400063

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400063
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths5 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jan 2029Dec 2030
Concrete structure (RCC)88%0%
Units booked91%42%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ranbir Green Path by Green Developers LLP is a 156-unit project in Goregaon East, Mumbai 400063, registered with MahaRERA in 2 phases, with possession due in January 2029. 142 units booked out of total 156 units. The concrete structure (RCC) is 88% complete.

Read full summary

Ranbir Green Path is a project by Green Developers LLP in Goregaon East, Mumbai 400063, registered with MahaRERA as 2 phases (P51800079703, P51800080759). The first phase was launched in March 2025. Together the phases have 156 units in 2 buildings: 131 homes (1 BHK) and 25 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.

The registered possession date is January 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 88% complete and final finishes 9% complete. Neither phase has its structure complete.

142 units booked out of total 156 units (91%).