Manjusha, Mulund West
by Yash Construction Co · Mulund West, Mumbai 400080 · Map
- Launched
- Mar 20252 yrs 3 mths promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 82%Mid-construction
- Booked (free sale)
- 13 of 3142%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale13 booked out of 31 units
Land-owner share16 units, not for sale
Total 47 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 21
- 2 BHK
- 17
- 3 BHK
- 9
- Total units
- 47
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Reserved units
- 9
- Free-sale units
- 31
- Land-owner share (not for sale)
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 82% | 0% | 13 | |
| 100% | 92% | 0% | 4 | |
| 100% | 82% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400080
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 3 mths | 2 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Jun 2027 | Mar 2028 |
| Concrete structure (RCC) | 82% | 0% |
| Units booked (free sale) | 42% | 33% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Stuti, Mulund West
- Aum Laxmi Kusum, Mulund West
- Ratan Laxmi Villa, Mulund West
- Omkar Sejal, Mulund West
- Ambe Mahal Centre One, Mulund West
- Sitaram Chsl, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Stuti | March 2025 | December 2027 | 0% | 15 units booked out of 40 units for sale |
| Aum Laxmi Kusum | April 2025 | December 2028 | 0% | – |
| Ratan Laxmi Villa | January 2025 | December 2026 | 90% | 21 units booked out of 72 units for sale |
| Omkar Sejal | June 2025 | June 2028 | 25% | 0 units booked out of 17 units for sale |
| Ambe Mahal Centre One | June 2025 | December 2028 | 0% | 111 units booked out of total 121 units |
| Sitaram Chsl | November 2024 | May 2027 | 0% | – |
About this project
Manjusha by Yash Construction Co is a 47-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in March 2025 with possession due in June 2027. 13 units booked out of 31 units for sale. The concrete structure (RCC) is 82% complete.
Read full summary
Manjusha is a BMC-sanctioned project by Yash Construction Co in Mulund West, Mumbai 400080, registered with MahaRERA as P51800079755. It was launched in March 2025. It has 47 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 47 units, 31 are for sale and 16 are the land-owner's share, not for sale.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 82% complete, final finishes not started.
13 units booked out of 31 units for sale (42%). Since the July 2026 update, 9 more units have been booked and the reported concrete structure (RCC) has gone from 92% to 82%.