Atlantis, Bhandup West
by Goldeneon Developers Private Limited · Bhandup West, Mumbai 400078 · Map
- Launched
- Mar 20258 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2033Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 23 of 18512% · 189 rehab units
- Buildings
- 30.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale23 booked out of 185 units
Rehab189 units for existing members
Total 374 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 311
- 2 BHK
- 16
- Other units
- 47
- Total units
- 374
- Buildings
- 3
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 185
- Rehab units
- 189
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 67% | 0% | 0% | 23 | |
| 53% | 0% | 0% | 12 | |
| 0% | 0% | 0% | 6 |
"–" means MahaRERA shows no figure for that update.
About this project
Atlantis by Goldeneon Developers Private Limited is a 374-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, launched in March 2025 with possession due in December 2033. 23 units booked out of 185 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Atlantis is an SRA-sanctioned project by Goldeneon Developers Private Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800079897. It was launched in March 2025. It has 374 units in 3 buildings: 327 homes (1 and 2 BHK) and 47 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 374 units, 185 are for sale and 189 are rehab units for existing members.
Its registered possession date is December 2033, unchanged since launch. Construction: excavation 67% complete, structure (RCC) not started, final finishes not started.
23 units booked out of 185 units for sale (12%). Since the July 2026 update, 11 more units have been booked.