Mickey Links, Malad West
by Jeetendra Murarilal Mody · Malad West, Mumbai 400064 · Map
- Launched
- Mar 20252 yrs 3 mths promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 87%Mid-construction
- Booked (free sale)
- 1 of 1010% · 1 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 10 units
Rehab1 unit for existing members
Land-owner share12 units, not for sale
Total 23 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 21
- Other units
- 2
- Total units
- 23
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 10
- Rehab units
- 1
- Land-owner share (not for sale)
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 87% | 0% | 1 | |
| 100% | 30% | 0% | 1 | |
| 75% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400064
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 3 mths | 3 yrs 4 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Jun 2027 | Sep 2028 |
| Concrete structure (RCC) | 87% | 68% |
| Units booked (free sale) | 10% | 54% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Rishab Aangan, Malad West
- Reyansh Infinity, Malad West
- Akash Chsl, Malad West
- Kanchan Villa Chsl, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rishab Aangan | March 2025 | June 2028 | 60% | 13 units booked out of 19 units for sale |
| Reyansh Infinity | January 2025 | December 2029 | 75% | 6 units booked out of 15 units for sale |
| Akash Chsl | November 2024 | June 2026 | 100% | 4 units booked out of 5 units for sale |
| Kanchan Villa Chsl | August 2025 | December 2028 | 60% | 0 units booked out of 7 units for sale |
About this project
Mickey Links by Jeetendra Murarilal Mody is a 23-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in March 2025 with possession due in June 2027. 1 unit booked out of 10 units for sale. The concrete structure (RCC) is 87% complete.
Read full summary
Mickey Links is a BMC-sanctioned project by Jeetendra Murarilal Mody in Malad West, Mumbai 400064, registered with MahaRERA as P51800079906. It was launched in March 2025. It has 23 units in 1 building: 21 homes (1 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 23 units, 10 are for sale, 1 is a rehab unit for existing members and 12 are the land-owner's share, not for sale.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 87% complete, final finishes not started.
1 unit booked out of 10 units for sale (10%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 30% to 87%.