Pearl Universe, Andheri West

by Chandiwala Enterprises Private Limited · Andheri West, Mumbai 400058 · Map

Launched
Apr 20255 yrs 8 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked
239 of 30080% · 197 in Jul 2026
Buildings
30.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
140
2 BHK
126
3 BHK
23
Other units
11
Total units
300
Buildings
3
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Reserved units
47

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 7%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%239
100%0%0%197
7%0%0%102

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Pearl Universe by Chandiwala Enterprises Private Limited is a 300-unit SRA-sanctioned project in Andheri West, Mumbai 400058, launched in April 2025 with possession due in December 2030. 239 units booked out of total 300 units. Work on the concrete structure (RCC) has not started.

Read full summary

Pearl Universe is an SRA-sanctioned project by Chandiwala Enterprises Private Limited in Andheri West, Mumbai 400058, registered with MahaRERA as P51800080142. It was launched in April 2025. It has 300 units in 3 buildings: 289 homes (1, 2 and 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

239 units booked out of total 300 units (80%). Since the July 2026 update, 42 more units have been booked.

Chandiwala's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA16
Total units across these projects3,068
Completed without extending the possession date7
Completed after an extension1
Lapsed0
Under construction8
Possession date extended on the builder's application1
Typical time from launch to 100% structure1 year 10 months
MahaRERA complaints (filed by or against the builder), all Chandiwala projects1 (1 of 16 projects)

See all Chandiwala projects →