Chandak Vansham, Vile Parle West
by Chandak Realtors Private Limited · Vile Parle West, Mumbai 400056 · Map
- Launched
- Apr 20256 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2031Not extended
- Concrete structure
- 3%Mid-construction
- Booked (free sale)
- 83 of 25233% · 273 rehab units
- Buildings
- 141.3 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale83 booked out of 252 units
Rehab273 units for existing members
Total 525 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 178
- 3 BHK
- 277
- 4 BHK
- 69
- Other units
- 1
- Total units
- 525
- Buildings
- 14
- Land
- 1.3 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 252
- Rehab units
- 273
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 76% | 3% | 0% | 83 | |
| 0% | 0% | 0% | 52 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Chandak Vansham by Chandak Realtors Private Limited is a 525-unit BMC-sanctioned project in Vile Parle West, Mumbai 400056, launched in April 2025 with possession due in December 2031. 83 units booked out of 252 units for sale. The concrete structure (RCC) is 3% complete.
Read full summary
Chandak Vansham is a BMC-sanctioned project by Chandak Realtors Private Limited in Vile Parle West, Mumbai 400056, registered with MahaRERA as P51800080145. It was launched in April 2025. It has 525 units in 14 buildings: 524 homes (2, 3 and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 525 units, 252 are for sale and 273 are rehab units for existing members.
Its registered possession date is December 2031, unchanged since launch. Construction: excavation 76% complete, structure (RCC) 3% complete, final finishes not started.
83 units booked out of 252 units for sale (33%). Since the July 2026 update, 31 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 3%.
Chandak's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 6 |
|---|---|
| Total units across these projects | 3,625 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 5 |
| Possession date extended on the builder's application | 0 |
| MahaRERA complaints (filed by or against the builder), all Chandak projects | 10 (3 of 6 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.