Skip to main content

Navrang Atlantis, Jogeshwari West

by Oxford Worldone Realty LLP · Jogeshwari West, Mumbai 400102 · Map

Launched
May 20253 yrs 8 mths promised
Possession (MahaRERA)
Jan 2029Not extended
Concrete structure
25%Mid-construction
Booked (free sale)
10 of 8012% · 40 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale10 booked out of 80 units

Rehab40 units for existing members

Total 120 units. Rehab units are not for sale.

Project facts

2 BHK
115
3 BHK
1
Other units
4
Total units
120
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
80
Rehab units
40

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)25%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 90%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 6%Oct 2026: Concrete structure (RCC) 25%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 25%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%25%0%10
100%6%0%7
90%0%0%7

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400102

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400102
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths5 yrs
Possession date extendedNo0 of 5
Possession date (MahaRERA)Jan 2029Dec 2029
Concrete structure (RCC)25%0%
Units booked (free sale)12%52%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Navrang Atlantis by Oxford Worldone Realty LLP is a 120-unit MHADA-sanctioned project in Jogeshwari West, Mumbai 400102, launched in May 2025 with possession due in January 2029. 10 units booked out of 80 units for sale. The concrete structure (RCC) is 25% complete.

Read full summary

Navrang Atlantis is a MHADA-sanctioned project by Oxford Worldone Realty LLP in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800080163. It was launched in May 2025. It has 120 units in 1 building: 116 homes (2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 120 units, 80 are for sale and 40 are rehab units for existing members.

Its registered possession date is January 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 25% complete, final finishes not started.

10 units booked out of 80 units for sale (12%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 6% to 25%.