by Ashirwad Nice Developers · Borivali West, Mumbai 400091 · Map

Launched
May 20254 yrs 1 mth promised
Possession (MahaRERA)
Jun 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
7 of 978% · 10 rehab units
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale7 booked out of 9 units

Rehab10 units for existing members

Total 19 units. Rehab units are not for sale.

Project facts

1 BHK
1
4 BHK
5
5+ BHK
1
Other units
12
Total units
19
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Rehab units
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 80%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%7
100%0%0%0
80%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Legacy by Ashirwad Nice Developers is a 19-unit BMC-sanctioned project in Borivali West, Mumbai 400091, launched in May 2025 with possession due in June 2029. 7 units booked out of 9 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Legacy is a BMC-sanctioned project by Ashirwad Nice Developers in Borivali West, Mumbai 400091, registered with MahaRERA as P51800080166. It was launched in May 2025. It has 19 units in 1 building: 7 homes (1, 4 and 5+ BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 19 units, 9 are for sale and 10 are rehab units for existing members.

Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

7 units booked out of 9 units for sale (78%). Since the July 2026 update, 7 more units have been booked.