Legacy, Borivali West
by Ashirwad Nice Developers · Borivali West, Mumbai 400091 · Map
- Launched
- May 20254 yrs 1 mth promised
- Possession (MahaRERA)
- Jun 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 7 of 978% · 10 rehab units
- Buildings
- 10.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale7 booked out of 9 units
Rehab10 units for existing members
Total 19 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 4 BHK
- 5
- 5+ BHK
- 1
- Other units
- 12
- Total units
- 19
- Buildings
- 1
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 9
- Rehab units
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 7 | |
| 100% | 0% | 0% | 0 | |
| 80% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Legacy by Ashirwad Nice Developers is a 19-unit BMC-sanctioned project in Borivali West, Mumbai 400091, launched in May 2025 with possession due in June 2029. 7 units booked out of 9 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Legacy is a BMC-sanctioned project by Ashirwad Nice Developers in Borivali West, Mumbai 400091, registered with MahaRERA as P51800080166. It was launched in May 2025. It has 19 units in 1 building: 7 homes (1, 4 and 5+ BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 19 units, 9 are for sale and 10 are rehab units for existing members.
Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
7 units booked out of 9 units for sale (78%). Since the July 2026 update, 7 more units have been booked.