Mamtora Embassy, Malad West

by Mamtora Constructions · Malad West, Mumbai 400064 · Map

Launched
Jun 20253 yrs promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
–No units for sale
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free saleNo units for sale

Rehab5 units for existing members

Total 5 units. Rehab units are not for sale.

Project facts

Other units
5
Total units
5
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1
Free-sale units
0
Rehab units
5

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%0
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Mamtora Embassy by Mamtora Constructions is a 5-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in June 2025 with possession due in June 2028. No units for sale: rehab units only. Work on the concrete structure (RCC) has not started.

Read full summary

Mamtora Embassy is a BMC-sanctioned project by Mamtora Constructions in Malad West, Mumbai 400064, registered with MahaRERA as P51800080422. It was launched in June 2025. It has 5 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 5 units, none is for sale and 5 are rehab units for existing members.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

No units for sale: rehab units only.