Ashish, Juhu

by Bhoomi Realty And Developers LLP · Juhu, Mumbai 400049 · Map

Launched
Jun 20252 yrs 1 mth promised
Possession (MahaRERA)
Jul 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
0 of 50%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 5 units

Land-owner share4 units, not for sale

Total 9 units. Land-owner units are not for sale.

Project facts

4 BHK
9
Total units
9
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
5
Land-owner share (not for sale)
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 20%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%0
100%100%20%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400049

Projects with up to 20 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 400049
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 1 mth4 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jul 2027Oct 2029
Concrete structure (RCC)100%0%
Units booked (free sale)0%31%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ashish by Bhoomi Realty And Developers LLP is a 9-unit SRA-sanctioned project in Juhu, Mumbai 400049, launched in June 2025 with possession due in July 2027. 0 units booked out of 5 units for sale. The concrete structure (RCC) is complete.

Read full summary

Ashish is an SRA-sanctioned project by Bhoomi Realty And Developers LLP in Juhu, Mumbai 400049, registered with MahaRERA as P51800080453. It was launched in June 2025. It has 9 units in 1 building, with 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 9 units, 5 are for sale and 4 are the land-owner's share, not for sale.

Its registered possession date is July 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

0 units booked out of 5 units for sale (0%).