Shri Hari Co-Op-Housing Society Ltd, Powai

by Devisri Enterprises Private Limited · Powai, Mumbai 400076 · Map

Launched
Jun 20252 yrs 6 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
60%Mid-construction
Booked
8 of 989%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
9
Total units
9
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 60%Jul 2026: Excavation 60%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 60%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%8
60%0%0%8
60%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Shri Hari Co-Op-Housing Society Ltd by Devisri Enterprises Private Limited is a 9-unit BMC-sanctioned project in Powai, Mumbai 400076, launched in June 2025 with possession due in December 2027. 8 units booked out of total 9 units. The concrete structure (RCC) is 60% complete.

Read full summary

Shri Hari Co-Op-Housing Society Ltd is a BMC-sanctioned project by Devisri Enterprises Private Limited in Powai, Mumbai 400076, registered with MahaRERA as P51800080462. It was launched in June 2025. It has 9 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.

8 units booked out of total 9 units (89%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 60%.