15 Park View, Khar West

by L Nagpal Developers · Khar West, Mumbai 400052 · Map

Launched
Jul 20252 yrs 8 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
80%Mid-construction
Booked (free sale)
4 of 667% · 12 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 6 units

Rehab12 units for existing members

Total 18 units. Rehab units are not for sale.

Project facts

2 BHK
4
3 BHK
10
4 BHK
2
5+ BHK
1
Other units
1
Total units
18
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
6
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 20%Jul 2026: Excavation 20%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 80%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 80%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%20%4
20%0%0%2
20%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400052

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400052
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 8 mths3 yrs
Possession date extendedNo0 of 4
Possession date (MahaRERA)Mar 2028Jun 2028
Concrete structure (RCC)80%15%
Units booked (free sale)67%42%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

15 Park View by L Nagpal Developers is an 18-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in July 2025 with possession due in March 2028. 4 units booked out of 6 units for sale. The concrete structure (RCC) is 80% complete.

Read full summary

15 Park View is a BMC-sanctioned project by L Nagpal Developers in Khar West, Mumbai 400052, registered with MahaRERA as P51800080779. It was launched in July 2025. It has 18 units in 1 building: 17 homes (2, 3, 4 and 5+ BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 18 units, 6 are for sale and 12 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 80% complete, final finishes 20% complete.

4 units booked out of 6 units for sale (67%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 80%.