Ozone Heritage, Jogeshwari West

by Blue Ocean Realty · Jogeshwari West, Mumbai 400102 · Map

Launched
Jul 20252 yrs 11 mths promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
85%Mid-construction
Booked (free sale)
38 of 4486% · 10 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale38 booked out of 44 units

Rehab10 units for existing members

Land-owner share5 units, not for sale

Total 59 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
31
2 BHK
12
3 BHK
2
Other units
14
Total units
59
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
44
Rehab units
10
Land-owner share (not for sale)
5
Reserved units
17

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)85%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 81%Oct 2026: Concrete structure (RCC) 85%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 85%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%0%38
100%81%0%2
100%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Ozone Heritage by Blue Ocean Realty is a 59-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, launched in July 2025 with possession due in June 2028. 38 units booked out of 44 units for sale. The concrete structure (RCC) is 85% complete.

Read full summary

Ozone Heritage is a BMC-sanctioned project by Blue Ocean Realty in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800080783. It was launched in July 2025. It has 59 units in 1 building: 45 homes (1, 2 and 3 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 59 units, 44 are for sale, 10 are rehab units for existing members and 5 are the land-owner's share, not for sale.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 85% complete, final finishes not started.

38 units booked out of 44 units for sale (86%). Since the July 2026 update, 36 more units have been booked and the reported concrete structure (RCC) has gone from 81% to 85%.