Green Nest, Goregaon East
by Bhavya Parshva Realty LLP · Goregaon East, Mumbai 400065 · Map
- Launched
- Jul 20253 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 22%Mid-construction
- Booked (free sale)
- 0 of 800% · 8 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 80 units
Rehab8 units for existing members
Total 88 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 40
- 2 BHK
- 40
- Other units
- 8
- Total units
- 88
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 80
- Rehab units
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 22% | 0% | 0 | |
| 100% | 22% | 0% | 0 | |
| 100% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
About this project
Green Nest by Bhavya Parshva Realty LLP is an 88-unit MHADA-sanctioned project in Goregaon East, Mumbai 400065, launched in July 2025 with possession due in December 2028. 0 units booked out of 80 units for sale. The concrete structure (RCC) is 22% complete.
Read full summary
Green Nest is a MHADA-sanctioned project by Bhavya Parshva Realty LLP in Goregaon East, Mumbai 400065, registered with MahaRERA as P51800080833. It was launched in July 2025. It has 88 units in 1 building: 80 homes (1 and 2 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 88 units, 80 are for sale and 8 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 22% complete, final finishes not started.
0 units booked out of 80 units for sale (0%).