Elevia, Chembur

by Vida Infrahub LLP · Chembur, Mumbai 400071 · Map

Launched
Aug 20256 yrs 4 mths promised
Possession (MahaRERA)
Dec 2031Not extended
Concrete structure
0%Early stage
Booked
284 of 42367%
Buildings
41.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
232
2 BHK
123
3 BHK
27
4 BHK
1
Other units
40
Total units
423
Buildings
4
Land
1.1 acres
Phases
1
MahaRERA complaints
0
Reserved units
259

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%284
0%0%0%284
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Elevia by Vida Infrahub LLP is a 423-unit SRA-sanctioned project in Chembur, Mumbai 400071, launched in August 2025 with possession due in December 2031. 284 units booked out of total 423 units. Work on the concrete structure (RCC) has not started.

Read full summary

Elevia is an SRA-sanctioned project by Vida Infrahub LLP in Chembur, Mumbai 400071, registered with MahaRERA as P51800080902. It was launched in August 2025. It has 423 units in 4 buildings: 383 homes (1, 2, 3 and 4 BHK) and 40 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2031, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

284 units booked out of total 423 units (67%).