B-1, E Wing, Andheri East

by Accord Land Developers Pvt Ltd · Andheri East, Mumbai 400093 · Map

Launched
Sep 20255 yrs 3 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
7%Mid-construction
Booked
3 of 615%
Buildings
16.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
11
2 BHK
38
3 BHK
12
Total units
61
Buildings
1
Land
6.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)7%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 90%Jul 2026: Excavation 90%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 7%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 7%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%7%0%3
90%0%0%–
90%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

B-1, E Wing by Accord Land Developers Pvt Ltd is a 61-unit SRA-sanctioned project in Andheri East, Mumbai 400093, launched in September 2025 with possession due in December 2030. 3 units booked out of total 61 units. The concrete structure (RCC) is 7% complete.

Read full summary

B-1, E Wing is an SRA-sanctioned project by Accord Land Developers Pvt Ltd in Andheri East, Mumbai 400093, registered with MahaRERA as P51800080967. It was launched in September 2025. It has 61 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 7% complete, final finishes not started.

3 units booked out of total 61 units (5%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 7%.