Greenstone Heritage, Fort

by Beauty Lifestyles and Homes Pvt Ltd · Fort, Mumbai 400001 · Map

Launched
Jul 2017First of 4 phases
Possession (MahaRERA)
Oct 2025 – Dec 2029Not extended
Concrete structure
71%Weighted across 4 phases
Booked (free sale)
–
Buildings
41.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale222 units; booked –

Rehab119 units for existing members

Land-owner share11 units, not for sale

Total 352 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
144
2 BHK
164
3 BHK
12
Other units
32
Total units
352
Buildings
4
Land
1.6 acres
Phases
4
MahaRERA complaints
0
Free-sale units
222
Rehab units
119
Land-owner share (not for sale)
11

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Greenstone Heritage - Wing - D
Nearing possession Lapsed
P5190000237256100%98%
Greenstone Heritage - Wing - E and F
Completed
P5190000830056100%–
Greenstone Heritage - Wing - I
Nearing possession
P51900055499112100%46%
Greenstone Heritage - B Wing
Mid-construction
PR1173032501584964%3%
Show updates by phase

Greenstone Heritage - Wing - D (P51900002372)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%72%55
100%100%72%–
100%100%60%51

"–" means MahaRERA shows no figure for that update.

Greenstone Heritage - Wing - E and F (P51900008300)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%52

"–" means MahaRERA shows no figure for that update.

Greenstone Heritage - Wing - I (P51900055499)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%61
100%11%0%52
100%11%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

Greenstone Heritage - B Wing (PR1173032501584)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%4%0%3
100%0%0%1
75%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)71%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 93%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 39%Jul 2026: Concrete structure (RCC) 39%Oct 2026: Concrete structure (RCC) 71%Dec 2025: Final finishes 30%Jul 2026: Final finishes 30%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 71%Final finishes 30%

How to read construction stages

About this project

Greenstone Heritage by Beauty Lifestyles and Homes Pvt Ltd is a 352-unit BMC-sanctioned project in Fort, Mumbai 400001, registered with MahaRERA in 4 phases, with possession dates from October 2025 to December 2029. The concrete structure (RCC) is 71% complete.

Read full summary

Greenstone Heritage is a BMC-sanctioned project by Beauty Lifestyles and Homes Pvt Ltd in Fort, Mumbai 400001, registered with MahaRERA as 4 phases (P51900002372, P51900008300, P51900055499, PR1173032501584). The first phase was launched in July 2017. Together the phases have 352 units in 4 buildings: 320 homes (1, 2 and 3 BHK) and 32 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 2 are active, 1 is lapsed and 1 is completed. Of the 352 units, 222 are for sale, 119 are rehab units for existing members and 11 are the land-owner's share, not for sale.

The phases' registered possession dates run from October 2025 to December 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 71% complete and final finishes 30% complete. 3 of the 4 phases have their structure complete.