Solstice Phase- I, Ghatkopar East

by Neelam Finance (Bombay ) Pvt Ltd · Ghatkopar East, Mumbai 400077 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2023Extended by 1 yr
Concrete structure
90%Mid-construction
Booked
297 of 33289%
Buildings
14.5 acres
MahaRERA complaints
6Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
100
2 BHK
96
3 BHK
136
Total units
332
Buildings
1
Land
4.5 acres
Phases
1
MahaRERA complaints
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)90%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 95%Dec 2025: Excavation 90%Jul 2026: Excavation 90%Dec 2024: Concrete structure (RCC) 92%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 71%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Excavation 90%Concrete structure (RCC) 90%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%90%80%297
90%90%80%293
95%92%71%291

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Solstice Phase- I by Neelam Finance (Bombay) Pvt Ltd is a 332-unit SRA-sanctioned project in Ghatkopar East, Mumbai 400077, launched in August 2017 with possession due in December 2023. 297 units booked out of total 332 units. The concrete structure (RCC) is 90% complete.

Read full summary

Solstice Phase- I is an SRA-sanctioned project by Neelam Finance (Bombay) Pvt Ltd in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51900002750. It was launched in August 2017. It has 332 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2023, after an extension of 1 year from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation 90% complete, structure (RCC) 90% complete, final finishes 80% complete.

297 units booked out of total 332 units (89%).