Rajhans, Dahisar

by Pratham Developers · Dahisar, Mumbai 400068 · Map

Launched
Aug 20172 yrs 4 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 7 yrs 4 mths
Concrete structure
45%Mid-construction
Booked (free sale)
2 of 2100% · 9 rehab units
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 2 units

Rehab9 units for existing members

Total 11 units. Rehab units are not for sale.

Project facts

1 BHK
8
2 BHK
3
Total units
11
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1
Free-sale units
2
Rehab units
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)45%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 45%Dec 2025: Concrete structure (RCC) 45%Jul 2026: Concrete structure (RCC) 45%Oct 2026: Concrete structure (RCC) 45%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 45%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%45%0%9
100%45%0%0
100%45%0%0
100%45%0%9

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Rajhans by Pratham Developers is an 11-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in August 2017 with possession due in April 2027. 2 units booked out of 2 units for sale. The concrete structure (RCC) is 45% complete.

Read full summary

Rajhans is a BMC-sanctioned project by Pratham Developers in Dahisar, Mumbai 400068, registered with MahaRERA as P51900002771. It was launched in August 2017. It has 11 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 11 units, 2 are for sale and 9 are rehab units for existing members.

Its registered possession date is April 2027, extended by 7 years 4 months from the original December 2019. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.

2 units booked out of 2 units for sale (100%). Since the July 2026 update, 2 more units have been booked and the possession date has moved from December 2020 to April 2027.