Skye 31, Wadala West

by B P Gangar Constructions Pvt Ltd · Wadala West, Mumbai 400031 · Map

Launched
Aug 20176 yrs 10 mths originally promised
Possession (MahaRERA)
Jun 2025Extended by 1 yr
Concrete structure
5%Mid-construction
Booked
138 of 15987%
Buildings
10.9 acres
MahaRERA complaints
31Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
159
Total units
159
Buildings
1
Land
0.9 acres
Phases
1
MahaRERA complaints
31

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)5%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 5%Jul 2026: Concrete structure (RCC) 5%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 5%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%5%0%138
100%5%0%138
100%0%0%135

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Skye 31 by B P Gangar Constructions Pvt Ltd is a 159-unit BMC-sanctioned project in Wadala West, Mumbai 400031, launched in August 2017 with possession due in June 2025. 138 units booked out of total 159 units. The concrete structure (RCC) is 5% complete.

Read full summary

Skye 31 is a BMC-sanctioned project by B P Gangar Constructions Pvt Ltd in Wadala West, Mumbai 400031, registered with MahaRERA as P51900002859. It was launched in August 2017. It has 159 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in June 2025, after an extension of 1 year from the original June 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 5% complete, final finishes not started.

138 units booked out of total 159 units (87%).