by Roxina Real Estate Pvt Ltd · Kalbadevi, Mumbai 400002 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 3 yrs 3 mths
- Concrete structure
- 53%Mid-construction
- Booked
- 108 of 21351%
- Buildings
- 11.4 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 103
- 2 BHK
- 83
- 3 BHK
- 27
- Total units
- 213
- Buildings
- 1
- Land
- 1.4 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 53% | 0% | 108 | |
| 100% | 53% | 0% | – | |
| 100% | 53% | 0% | – | |
| 100% | 53% | 0% | 108 |
"–" means MahaRERA shows no figure for that update.
About this project
Lifescapes Kshitij by Roxina Real Estate Pvt Ltd is a 213-unit project in Kalbadevi, Mumbai 400002, launched in August 2017 with possession due in March 2027. 108 units booked out of total 213 units. The concrete structure (RCC) is 53% complete.
Read full summary
Lifescapes Kshitij is a project by Roxina Real Estate Pvt Ltd in Kalbadevi, Mumbai 400002, registered with MahaRERA as P51900004172. It was launched in August 2017. It has 213 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2027, extended by 3 years 3 months from the original December 2023. Construction: excavation complete, structure (RCC) 53% complete, final finishes not started.
108 units booked out of total 213 units (51%).