M4 Aarambh, Girgaon
by M4 Realty LLP · Girgaon, Mumbai 400004 · Map
- Launched
- Aug 20177 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 2 yrs
- Concrete structure
- 18%Mid-construction
- Booked
- 1 of 186%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 3
- 1 BHK
- 3
- 2 BHK
- 2
- 3 BHK
- 10
- Total units
- 18
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 18% | 65% | 1 | |
| 100% | 18% | 65% | – | |
| 100% | 18% | 65% | – | |
| 100% | 18% | 65% | 1 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400004
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 7 yrs 4 mths | 5 yrs 4 mths |
| Possession date extended | By 2 yrs | 3 of 3 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2023 |
| Concrete structure (RCC) | 18% | 100% |
| MahaRERA complaints (filed by or against the builder) | 1 | 2 |
The 3 projects
- Neo Amity, Girgaon
- Anantaya Apartments, Girgaon
- Neo Galaxy, Girgaon
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Neo Amity | August 2017 | December 2026 | 100% | 4 units booked out of total 60 units |
| Anantaya Apartments | August 2017 | December 2022 | 100% | – |
| Neo Galaxy | August 2017 | December 2023 | 90% | – |
About this project
M4 Aarambh by M4 Realty LLP is an 18-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in August 2017 with possession due in December 2026. 1 unit booked out of total 18 units. The concrete structure (RCC) is 18% complete.
Read full summary
M4 Aarambh is a BMC-sanctioned project by M4 Realty LLP in Girgaon, Mumbai 400004, registered with MahaRERA as P51900004211. It was launched in August 2017. It has 18 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) 18% complete, final finishes 65% complete.
1 unit booked out of total 18 units (6%).