Harbour Heights, Mazgaon
by Shree Naman Estate Projects Private Limited · Mazgaon, Mumbai 400010 · Map
- Launched
- Aug 20179 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 69.6 acres
- MahaRERA complaints
- 25Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 6
- Total units
- 6
- Buildings
- 6
- Land
- 9.6 acres
- Phases
- 1
- MahaRERA complaints
- 25
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 48% | 0% | 0% | 172 | |
| 46% | 0% | 0% | 172 |
"–" means MahaRERA shows no figure for that update.
About this project
Harbour Heights by Shree Naman Estate Projects Private Limited is a 6-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in August 2017 with possession due in December 2026. Work on the concrete structure (RCC) has not started.
Read full summary
Harbour Heights is a BMC-sanctioned project by Shree Naman Estate Projects Private Limited in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900004243. It was launched in August 2017. It has 6 units in 6 buildings, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation 48% complete, structure (RCC) not started, final finishes not started.