El Mejor, Dadar East

Ready to move

by Arth Realtech Spaces Pvt Ltd · Dadar East, Mumbai 400014 · Map

Launched
Aug 20173 yrs 7 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 5 yrs 9 mths
Concrete structure
100%Ready to move
Booked (free sale)
57 of 7675% · 39 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale57 booked out of 76 units

Rehab39 units for existing members

Total 115 units. Rehab units are not for sale.

Project facts

1 BHK
1
2 BHK
82
3 BHK
22
4 BHK
4
Other units
6
Total units
115
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
76
Rehab units
39

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 95%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 15%Dec 2025: Final finishes 85%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%57
100%100%100%57
100%100%85%56
100%95%15%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

El Mejor by Arth Realtech Spaces Pvt Ltd is a 115-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in August 2017 with possession due in December 2026. 57 units booked out of 76 units for sale. The concrete structure (RCC) is complete.

Read full summary

El Mejor is a BMC-sanctioned project by Arth Realtech Spaces Pvt Ltd in Dadar East, Mumbai 400014, registered with MahaRERA as P51900004688. It was launched in August 2017. It has 115 units in 1 building: 109 homes (1, 2, 3 and 4 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 115 units, 76 are for sale and 39 are rehab units for existing members.

Its registered possession date is December 2026, extended by 5 years 9 months from the original March 2021. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

57 units booked out of 76 units for sale (75%).