Atlantis Residency, Kalachowki
by Jk Builders · Kalachowki, Mumbai 400033 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 3 yrs 4 mths
- Concrete structure
- 88%Mid-construction
- Booked (free sale)
- 28 of 5551% · 106 rehab units
- Buildings
- 20.5 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale28 booked out of 55 units
Rehab106 units for existing members
Total 161 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 107
- 2 BHK
- 12
- 3 BHK
- 28
- Other units
- 14
- Total units
- 161
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 55
- Rehab units
- 106
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 88% | 0% | 28 | |
| 100% | 88% | 0% | 28 | |
| 100% | 90% | 0% | 13 | |
| 100% | 90% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Atlantis Residency by Jk Builders is a 161-unit BMC-sanctioned project in Kalachowki, Mumbai 400033, launched in August 2017 with possession due in April 2027. 28 units booked out of 55 units for sale. The concrete structure (RCC) is 88% complete.
Read full summary
Atlantis Residency is a BMC-sanctioned project by Jk Builders in Kalachowki, Mumbai 400033, registered with MahaRERA as P51900005501. It was launched in August 2017. It has 161 units in 2 buildings: 147 homes (1, 2 and 3 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 161 units, 55 are for sale and 106 are rehab units for existing members.
Its registered possession date is April 2027, extended by 3 years 4 months from the original December 2023. Construction: excavation complete, structure (RCC) 88% complete, final finishes not started.
28 units booked out of 55 units for sale (51%).