Saivishwa, Chembur

by Snehalkumar Chandrakant Nadkarni · Chembur, Mumbai 400089 · Map

Launched
Aug 20172 yrs 4 mths originally promised
Possession (MahaRERA)
Jun 2028Extended by 8 yrs 6 mths
Concrete structure
76%Mid-construction
Booked (free sale)
16 of 2467%
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale16 booked out of 24 units

Land-owner share4 units, not for sale

Total 28 units. Land-owner units are not for sale.

Project facts

1 BHK
26
3 BHK
2
Total units
28
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1
Free-sale units
24
Land-owner share (not for sale)
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)76%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 70%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 76%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 76%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%76%0%16
100%70%0%16
100%70%0%16
100%70%0%14

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Saivishwa by Snehalkumar Chandrakant Nadkarni is a 28-unit BMC-sanctioned project in Chembur, Mumbai 400089, launched in August 2017 with possession due in June 2028. 16 units booked out of 24 units for sale. The concrete structure (RCC) is 76% complete.

Read full summary

Saivishwa is a BMC-sanctioned project by Snehalkumar Chandrakant Nadkarni in Chembur, Mumbai 400089, registered with MahaRERA as P51900005928. It was launched in August 2017. It has 28 units in 1 building, with 1 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 28 units, 24 are for sale and 4 are the land-owner's share, not for sale.

Its registered possession date is June 2028, extended by 8 years 6 months from the original December 2019. Construction: excavation complete, structure (RCC) 76% complete, final finishes not started.

16 units booked out of 24 units for sale (67%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 70% to 76% and the possession date has moved from June 2025 to June 2028.