Dilkap Grandeur, Powai

by Dilip Estate & Town Planners Pvt Ltd · Powai, Mumbai 400076 · Map

Launched
Aug 20175 yrs 10 mths originally promised
Possession (MahaRERA)
Nov 2026Extended by 3 yrs 5 mths
Concrete structure
100%Nearing possession
Booked
28 of 4267%
Buildings
11 acre
MahaRERA complaints
9Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
24
4 BHK
18
Total units
42
Buildings
1
Land
1 acre
Phases
1
MahaRERA complaints
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 95%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 10%Jul 2026: Final finishes 10%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 100%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%28
100%100%10%28
100%100%10%28
100%95%0%27

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Dilkap Grandeur by Dilip Estate & Town Planners Pvt Ltd is a 42-unit BMC-sanctioned project in Powai, Mumbai 400076, launched in August 2017 with possession due in November 2026. 28 units booked out of total 42 units. The concrete structure (RCC) is complete.

Read full summary

Dilkap Grandeur is a BMC-sanctioned project by Dilip Estate & Town Planners Pvt Ltd in Powai, Mumbai 400076, registered with MahaRERA as P51900006119. It was launched in August 2017. It has 42 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is November 2026, extended by 3 years 5 months from the original June 2023. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.

28 units booked out of total 42 units (67%).