Crystal Vue, Wadala East
by Nageshwar V Neela · Wadala East, Mumbai 400037 · Map
- Launched
- Aug 20178 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 2 yrs
- Concrete structure
- 68%Mid-construction
- Booked (free sale)
- 11 of 4524%
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale11 booked out of 45 units
Land-owner share8 units, not for sale
Total 53 units. Land-owner units are not for sale.
Project facts
- 3 BHK
- 21
- 4 BHK
- 21
- 5+ BHK
- 11
- Total units
- 53
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 45
- Land-owner share (not for sale)
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 68% | 0% | 11 | |
| 100% | 64% | 0% | 0 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Crystal Vue by Nageshwar V Neela is a 53-unit SRA-sanctioned project in Wadala East, Mumbai 400037, launched in August 2017 with possession due in December 2027. 11 units booked out of 45 units for sale. The concrete structure (RCC) is 68% complete.
Read full summary
Crystal Vue is an SRA-sanctioned project by Nageshwar V Neela in Wadala East, Mumbai 400037, registered with MahaRERA as P51900006774. It was launched in August 2017. It has 53 units in 1 building, with 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 53 units, 45 are for sale and 8 are the land-owner's share, not for sale.
Its registered possession date is December 2027, extended by 2 years from the original December 2025. Construction: excavation complete, structure (RCC) 68% complete, final finishes not started.
11 units booked out of 45 units for sale (24%). Since the July 2026 update, 11 more units have been booked and the reported concrete structure (RCC) has gone from 64% to 68%.