Ready to move

by Imran Ali Mohammed Latif · Mandvi, Mumbai 400003 · Map

Launched
Aug 20174 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 6 yrs
Concrete structure
100%Ready to move
Booked (free sale)
75 of 10174% · 133 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale75 booked out of 101 units

Rehab133 units for existing members

Total 234 units. Rehab units are not for sale.

Project facts

1 RK
3
1 BHK
85
2 BHK
68
3 BHK
23
Other units
55
Total units
234
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
101
Rehab units
133

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services98%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 70%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 60%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 98%Excavation 100%Concrete structure (RCC) 100%Final finishes 98%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%98%75
100%100%95%75
100%100%95%–
100%70%60%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Burj Ashrafi by Imran Ali Mohammed Latif is a 234-unit BMC-sanctioned project in Mandvi, Mumbai 400003, launched in August 2017 with possession due in December 2027. 75 units booked out of 101 units for sale. The concrete structure (RCC) is complete.

Read full summary

Burj Ashrafi is a BMC-sanctioned project by Imran Ali Mohammed Latif in Mandvi, Mumbai 400003, registered with MahaRERA as P51900007321. It was launched in August 2017. It has 234 units in 1 building: 179 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 55 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 234 units, 101 are for sale and 133 are rehab units for existing members.

Its registered possession date is December 2027, extended by 6 years from the original December 2021. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

75 units booked out of 101 units for sale (74%).