- Launched
- Aug 20174 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 6 yrs
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 75 of 10174% · 133 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale75 booked out of 101 units
Rehab133 units for existing members
Total 234 units. Rehab units are not for sale.
Project facts
- 1 RK
- 3
- 1 BHK
- 85
- 2 BHK
- 68
- 3 BHK
- 23
- Other units
- 55
- Total units
- 234
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 101
- Rehab units
- 133
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 98% | 75 | |
| 100% | 100% | 95% | 75 | |
| 100% | 100% | 95% | – | |
| 100% | 70% | 60% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Burj Ashrafi by Imran Ali Mohammed Latif is a 234-unit BMC-sanctioned project in Mandvi, Mumbai 400003, launched in August 2017 with possession due in December 2027. 75 units booked out of 101 units for sale. The concrete structure (RCC) is complete.
Read full summary
Burj Ashrafi is a BMC-sanctioned project by Imran Ali Mohammed Latif in Mandvi, Mumbai 400003, registered with MahaRERA as P51900007321. It was launched in August 2017. It has 234 units in 1 building: 179 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 55 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 234 units, 101 are for sale and 133 are rehab units for existing members.
Its registered possession date is December 2027, extended by 6 years from the original December 2021. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
75 units booked out of 101 units for sale (74%).