Al Amir Apartment, Chinchbunder
by Janzeb Amirkamal Khan · Chinchbunder, Mumbai 400009 · Map
- Launched
- Aug 20175 yrs 11 mths originally promised
- Possession (MahaRERA)
- Dec 2028Extended by 5 yrs 5 mths
- Concrete structure
- 89%Mid-construction
- Booked (free sale)
- 108 of 12090% · 128 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale108 booked out of 120 units
Rehab128 units for existing members
Total 248 units. Rehab units are not for sale.
Project facts
- 1 RK
- 157
- 1 BHK
- 58
- 2 BHK
- 15
- 3 BHK
- 1
- Other units
- 17
- Total units
- 248
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 120
- Rehab units
- 128
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 89% | 78% | 108 | |
| 50% | 45% | 39% | – | |
| 50% | 45% | 39% | – | |
| 100% | 89% | 78% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Al Amir Apartment by Janzeb Amirkamal Khan is a 248-unit BMC-sanctioned project in Chinchbunder, Mumbai 400009, launched in August 2017 with possession due in December 2028. 108 units booked out of 120 units for sale. The concrete structure (RCC) is 89% complete.
Read full summary
Al Amir Apartment is a BMC-sanctioned project by Janzeb Amirkamal Khan in Chinchbunder, Mumbai 400009, registered with MahaRERA as P51900007426. It was launched in August 2017. It has 248 units in 1 building: 231 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 248 units, 120 are for sale and 128 are rehab units for existing members.
Its registered possession date is December 2028, extended by 5 years 5 months from the original July 2023. Construction: excavation complete, structure (RCC) 89% complete, final finishes 78% complete.
108 units booked out of 120 units for sale (90%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 45% to 89% and the possession date has moved from July 2024 to December 2028.