Panchratna-Nx, Dadar East
by Sudhir Kishor Desai · Dadar East, Mumbai 400014 · Map
- Launched
- Aug 20173 yrs 10 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 5 yrs 10 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 30 of 5357% · 77 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale30 booked out of 53 units
Rehab77 units for existing members
Total 130 units. Rehab units are not for sale.
Project facts
- 1 RK
- 3
- 1 BHK
- 66
- 2 BHK
- 30
- 3 BHK
- 6
- Other units
- 25
- Total units
- 130
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 53
- Rehab units
- 77
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 63% | 30 | |
| 100% | 100% | 63% | 30 | |
| 100% | 100% | 15% | 30 | |
| 100% | 100% | 15% | 26 |
"–" means MahaRERA shows no figure for that update.
About this project
Panchratna-Nx by Sudhir Kishor Desai is a 130-unit SRA-sanctioned project in Dadar East, Mumbai 400014, launched in August 2017 with possession due in April 2027. 30 units booked out of 53 units for sale. The concrete structure (RCC) is complete.
Read full summary
Panchratna-Nx is an SRA-sanctioned project by Sudhir Kishor Desai in Dadar East, Mumbai 400014, registered with MahaRERA as P51900007684. It was launched in August 2017. It has 130 units in 2 buildings: 105 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 25 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 130 units, 53 are for sale and 77 are rehab units for existing members.
Its registered possession date is April 2027, extended by 5 years 10 months from the original June 2021. Construction: excavation complete, structure (RCC) complete, final finishes 63% complete.
30 units booked out of 53 units for sale (57%).