Eiffel Tower, Mazgaon

by Empress Developers · Mazgaon, Mumbai 400010 · Map

Launched
Aug 20175 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 4 yrs 6 mths
Concrete structure
92%Mid-construction
Booked
–
Buildings
10.8 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)92%
Finishes, lifts and services40%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 90%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 92%Dec 2025: Concrete structure (RCC) 92%Jul 2026: Concrete structure (RCC) 92%Dec 2024: Final finishes 25%Dec 2025: Final finishes 40%Jul 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 92%Final finishes 40%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%92%40%–
100%92%40%–
90%92%25%69

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Eiffel Tower by Empress Developers is a project in Mazgaon, Mumbai 400010, launched in August 2017 with possession due in December 2027. The concrete structure (RCC) is 92% complete.

Read full summary

Eiffel Tower is a project by Empress Developers in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900007758. It was launched in August 2017. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 4 years 6 months from the original June 2023. Construction: excavation complete, structure (RCC) 92% complete, final finishes 40% complete.