- Launched
- Aug 20175 yrs 11 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 3 yrs 5 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 13 of 2357% · 8 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale13 booked out of 23 units
Rehab8 units for existing members
Total 31 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 28
- Other units
- 3
- Total units
- 31
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 23
- Rehab units
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 13 | |
| 100% | 100% | 90% | 13 | |
| 100% | 100% | 75% | 12 | |
| 100% | 70% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
About this project
J K Apartment by Plus Properties Pvt Ltd is a 31-unit BMC-sanctioned project in Sewri, Mumbai 400015, launched in August 2017 with possession due in December 2026. 13 units booked out of 23 units for sale. The concrete structure (RCC) is complete.
Read full summary
J K Apartment is a BMC-sanctioned project by Plus Properties Pvt Ltd in Sewri, Mumbai 400015, registered with MahaRERA as P51900008108. It was launched in August 2017. It has 31 units in 1 building: 28 homes (1 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 31 units, 23 are for sale and 8 are rehab units for existing members.
Its registered possession date is December 2026, extended by 3 years 5 months from the original July 2023. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
13 units booked out of 23 units for sale (57%).