Minerva, Mahalaxmi
by Lokhandwala Kataria Construction Private Limited · Mahalaxmi, Mumbai 400011 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2024Extended by 1 yr
- Concrete structure
- 99%Mid-construction
- Booked
- 304 of 37282%
- Buildings
- 32 acres
- MahaRERA complaints
- 53Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 200
- 4 BHK
- 164
- Other units
- 8
- Total units
- 372
- Buildings
- 3
- Land
- 2 acres
- Phases
- 1
- MahaRERA complaints
- 53
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 99% | 62% | 304 | |
| 100% | 99% | 62% | 296 | |
| 100% | 99% | 62% | 287 |
"–" means MahaRERA shows no figure for that update.
About this project
Minerva by Lokhandwala Kataria Construction Private Limited is a 372-unit SRA-sanctioned project in Mahalaxmi, Mumbai 400011, launched in August 2017 with possession due in December 2024. 304 units booked out of total 372 units. The concrete structure (RCC) is 99% complete.
Read full summary
Minerva is an SRA-sanctioned project by Lokhandwala Kataria Construction Private Limited in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900008204. It was launched in August 2017. It has 372 units in 3 buildings: 364 homes (3 and 4 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 99% complete, final finishes 62% complete.
304 units booked out of total 372 units (82%).