by Lokhandwala Kataria Construction Private Limited · Mahalaxmi, Mumbai 400011 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 1 yr
Concrete structure
99%Mid-construction
Booked
304 of 37282%
Buildings
32 acres
MahaRERA complaints
53Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
200
4 BHK
164
Other units
8
Total units
372
Buildings
3
Land
2 acres
Phases
1
MahaRERA complaints
53

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)99%
Finishes, lifts and services62%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 99%Dec 2025: Concrete structure (RCC) 99%Jul 2026: Concrete structure (RCC) 99%Dec 2024: Final finishes 62%Dec 2025: Final finishes 62%Jul 2026: Final finishes 62%Excavation 100%Concrete structure (RCC) 99%Final finishes 62%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%99%62%304
100%99%62%296
100%99%62%287

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Minerva by Lokhandwala Kataria Construction Private Limited is a 372-unit SRA-sanctioned project in Mahalaxmi, Mumbai 400011, launched in August 2017 with possession due in December 2024. 304 units booked out of total 372 units. The concrete structure (RCC) is 99% complete.

Read full summary

Minerva is an SRA-sanctioned project by Lokhandwala Kataria Construction Private Limited in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900008204. It was launched in August 2017. It has 372 units in 3 buildings: 364 homes (3 and 4 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 99% complete, final finishes 62% complete.

304 units booked out of total 372 units (82%).