Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited, Mulund East
by Shubh Prabhav Infracom LLP · Mulund East, Mumbai 400081 · Map
- Launched
- Aug 20175 yrs 4 mths originally promised
- Possession (MahaRERA)
- Jun 2030Extended by 7 yrs 6 mths
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 10.4 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Total units
- –
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 63 | |
| 0% | 0% | 0% | 63 |
"–" means MahaRERA shows no figure for that update.
About this project
Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited by Shubh Prabhav Infracom LLP is a BMC-sanctioned project in Mulund East, Mumbai 400081, launched in August 2017 with possession due in June 2030. Work on the concrete structure (RCC) has not started.
Read full summary
Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited is a BMC-sanctioned project by Shubh Prabhav Infracom LLP in Mulund East, Mumbai 400081, registered with MahaRERA as P51900008403. It was launched in August 2017. Its MahaRERA status is Active.
Its registered possession date is June 2030, extended by 7 years 6 months from the original December 2022. Construction: excavation not started, structure (RCC) not started, final finishes not started.
Since the December 2024 update, the possession date has moved from December 2022 to June 2030.