Elegant Residency, Mumbai Central

Ready to move

by Best Enterprises · Mumbai Central, Mumbai 400008 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 4 yrs
Concrete structure
100%Ready to move
Booked (free sale)
45 of 5582% · 56 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale45 booked out of 55 units

Rehab56 units for existing members

Total 111 units. Rehab units are not for sale.

Project facts

Other units
111
Total units
111
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
55
Rehab units
56

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services94%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 94%Excavation 100%Concrete structure (RCC) 100%Final finishes 94%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%94%45
100%100%95%44
100%100%95%–
100%100%95%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Elegant Residency by Best Enterprises is a 111-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in August 2017 with possession due in December 2027. 45 units booked out of 55 units for sale. The concrete structure (RCC) is complete.

Read full summary

Elegant Residency is a BMC-sanctioned project by Best Enterprises in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900008636. It was launched in August 2017. It has 111 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 111 units, 55 are for sale and 56 are rehab units for existing members.

Its registered possession date is December 2027, extended by 4 years from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 94% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

45 units booked out of 55 units for sale (82%). Since the July 2026 update, 1 more unit has been booked.