Vardhman Flora Phase I, Kalachowki

by Vardhman Developers Ltd · Kalachowki, Mumbai 400033 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 1 yr
Concrete structure
72%Mid-construction
Booked
73 of 11365%
Buildings
11.2 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
74
3 BHK
39
Total units
113
Buildings
1
Land
1.2 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)72%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 61%Dec 2025: Concrete structure (RCC) 72%Jul 2026: Concrete structure (RCC) 72%Dec 2024: Final finishes 0%Dec 2025: Final finishes 20%Jul 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 72%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%72%20%73
100%72%20%–
100%61%0%16

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vardhman Flora Phase I by Vardhman Developers Ltd is a 113-unit BMC-sanctioned project in Kalachowki, Mumbai 400033, launched in August 2017 with possession due in December 2024. 73 units booked out of total 113 units. The concrete structure (RCC) is 72% complete.

Read full summary

Vardhman Flora Phase I is a BMC-sanctioned project by Vardhman Developers Ltd in Kalachowki, Mumbai 400033, registered with MahaRERA as P51900008829. It was launched in August 2017. It has 113 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 72% complete, final finishes 20% complete.

73 units booked out of total 113 units (65%).