Pier 23, Mazgaon
by Hoor Constructions · Mazgaon, Mumbai 400010 · Map
- Launched
- Aug 20176 yrs 10 mths originally promised
- Possession (MahaRERA)
- Apr 2031Extended by 6 yrs 10 mths
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 20.6 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Total units
- –
- Buildings
- 2
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 2% | 0% | 0% | 24 | |
| 2% | 0% | 0% | 24 |
"–" means MahaRERA shows no figure for that update.
About this project
Pier 23 by Hoor Constructions is a BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in August 2017 with possession due in April 2031. Work on the concrete structure (RCC) has not started.
Read full summary
Pier 23 is a BMC-sanctioned project by Hoor Constructions in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900009360. It was launched in August 2017. Its MahaRERA status is Active.
Its registered possession date is April 2031, extended by 6 years 10 months from the original June 2024. Construction: excavation 2% complete, structure (RCC) not started, final finishes not started.
Since the December 2024 update, the possession date has moved from June 2024 to April 2031.