Skip to main content

Pier 23, Mazgaon

by Hoor Constructions · Mazgaon, Mumbai 400010 · Map

Launched
Aug 20176 yrs 10 mths originally promised
Possession (MahaRERA)
Apr 2031Extended by 6 yrs 10 mths
Concrete structure
0%Early stage
Booked
–
Buildings
20.6 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
2
Land
0.6 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation2%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Oct 2026Dec 2024: Excavation 2%Oct 2026: Excavation 2%Dec 2024: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Oct 2026: Final finishes 0%Excavation 2%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
2%0%0%24
2%0%0%24

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Pier 23 by Hoor Constructions is a BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in August 2017 with possession due in April 2031. Work on the concrete structure (RCC) has not started.

Read full summary

Pier 23 is a BMC-sanctioned project by Hoor Constructions in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900009360. It was launched in August 2017. Its MahaRERA status is Active.

Its registered possession date is April 2031, extended by 6 years 10 months from the original June 2024. Construction: excavation 2% complete, structure (RCC) not started, final finishes not started.

Since the December 2024 update, the possession date has moved from June 2024 to April 2031.