Prestige Nautilus, Worli
by Prestige Falcon Mumbai Realty Private Limited · Worli, Mumbai 400030 · Map
- Launched
- Aug 20178 yrs 4 mths originally promised
- Possession (MahaRERA)
- Jun 2032Extended by 6 yrs 6 mths
- Concrete structure
- 0%Early stage
- Booked
- 143 of 21467% · 138 in Jul 2026
- Buildings
- 31.9 acres
- MahaRERA complaints
- 16Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 21
- 4 BHK
- 135
- 5+ BHK
- 58
- Total units
- 214
- Buildings
- 3
- Land
- 1.9 acres
- Phases
- 1
- MahaRERA complaints
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 34% | 0% | 0% | 143 | |
| 10% | 0% | 0% | 138 | |
| 10% | 0% | 0% | 93 | |
| 30% | 0% | 0% | 18 |
"–" means MahaRERA shows no figure for that update.
About this project
Prestige Nautilus by Prestige Falcon Mumbai Realty Private Limited is a 214-unit MHADA-sanctioned project in Worli, Mumbai 400030, launched in August 2017 with possession due in June 2032. 143 units booked out of total 214 units. Work on the concrete structure (RCC) has not started.
Read full summary
Prestige Nautilus is a MHADA-sanctioned project by Prestige Falcon Mumbai Realty Private Limited in Worli, Mumbai 400030, registered with MahaRERA as P51900009720. It was launched in August 2017. It has 214 units in 3 buildings, with 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2032, extended by 6 years 6 months from the original December 2025. Construction: excavation 34% complete, structure (RCC) not started, final finishes not started.
143 units booked out of total 214 units (67%). Since the July 2026 update, 5 more units have been booked.
Prestige's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 15 |
|---|---|
| Total units across these projects | 5,057 |
| Completed without extending the possession date | 3 |
| Completed after an extension | 1 |
| Lapsed | 0 |
| Under construction | 11 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Prestige projects | 33 (5 of 15 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.