Prestige Nautilus, Worli

by Prestige Falcon Mumbai Realty Private Limited · Worli, Mumbai 400030 · Map

Launched
Aug 20178 yrs 4 mths originally promised
Possession (MahaRERA)
Jun 2032Extended by 6 yrs 6 mths
Concrete structure
0%Early stage
Booked
143 of 21467% · 138 in Jul 2026
Buildings
31.9 acres
MahaRERA complaints
16Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
21
4 BHK
135
5+ BHK
58
Total units
214
Buildings
3
Land
1.9 acres
Phases
1
MahaRERA complaints
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation34%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 30%Dec 2025: Excavation 10%Jul 2026: Excavation 10%Oct 2026: Excavation 34%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 34%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
34%0%0%143
10%0%0%138
10%0%0%93
30%0%0%18

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Prestige Nautilus by Prestige Falcon Mumbai Realty Private Limited is a 214-unit MHADA-sanctioned project in Worli, Mumbai 400030, launched in August 2017 with possession due in June 2032. 143 units booked out of total 214 units. Work on the concrete structure (RCC) has not started.

Read full summary

Prestige Nautilus is a MHADA-sanctioned project by Prestige Falcon Mumbai Realty Private Limited in Worli, Mumbai 400030, registered with MahaRERA as P51900009720. It was launched in August 2017. It has 214 units in 3 buildings, with 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2032, extended by 6 years 6 months from the original December 2025. Construction: excavation 34% complete, structure (RCC) not started, final finishes not started.

143 units booked out of total 214 units (67%). Since the July 2026 update, 5 more units have been booked.

Prestige's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA15
Total units across these projects5,057
Completed without extending the possession date3
Completed after an extension1
Lapsed0
Under construction11
Possession date extended on the builder's application2
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Prestige projects33 (5 of 15 projects)

See all Prestige projects →