Fortune Aura, Grant Road

Ready to move

by K Realtors · Grant Road, Mumbai 400007 · Map

Launched
Aug 20173 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2023Extended by 3 yrs
Concrete structure
100%Ready to move
Booked (free sale)
23 of 2882%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale23 booked out of 28 units

Land-owner share39 units, not for sale

Total 67 units. Land-owner units are not for sale.

Project facts

1 BHK
33
2 BHK
22
3 BHK
2
Other units
10
Total units
67
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
28
Land-owner share (not for sale)
39

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 86%Dec 2025: Final finishes 86%Jul 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%23
100%100%86%–
100%100%86%7

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Fortune Aura by K Realtors is a 67-unit BMC-sanctioned project in Grant Road, Mumbai 400007, launched in August 2017 with possession due in December 2023. 23 units booked out of 28 units for sale. The concrete structure (RCC) is complete.

Read full summary

Fortune Aura is a BMC-sanctioned project by K Realtors in Grant Road, Mumbai 400007, registered with MahaRERA as P51900010489. It was launched in August 2017. It has 67 units in 1 building: 57 homes (1, 2 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 67 units, 28 are for sale and 39 are the land-owner's share, not for sale.

Possession was due in December 2023, after an extension of 3 years from the original December 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

23 units booked out of 28 units for sale (82%).