Aura Bliss, Wadala West
by Aura Monde LLP · Wadala West, Mumbai 400031 · Map
- Launched
- Sep 20176 yrs 9 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 3 yrs 6 mths
- Concrete structure
- 40%Mid-construction
- Booked (free sale)
- 4 of 1331% · 21 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 13 units
Rehab21 units for existing members
Total 34 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 27
- 2 BHK
- 7
- Total units
- 34
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 13
- Rehab units
- 21
- Reserved units
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 40% | 0% | 4 | |
| 100% | 30% | 0% | 4 | |
| 100% | 15% | 0% | 0 | |
| 85% | 10% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Aura Bliss by Aura Monde LLP is a 34-unit BMC-sanctioned project in Wadala West, Mumbai 400031, launched in September 2017 with possession due in December 2027. 4 units booked out of 13 units for sale. The concrete structure (RCC) is 40% complete.
Read full summary
Aura Bliss is a BMC-sanctioned project by Aura Monde LLP in Wadala West, Mumbai 400031, registered with MahaRERA as P51900012309. It was launched in September 2017. It has 34 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 34 units, 13 are for sale and 21 are rehab units for existing members.
Its registered possession date is December 2027, extended by 3 years 6 months from the original June 2024. Construction: excavation complete, structure (RCC) 40% complete, final finishes not started.
4 units booked out of 13 units for sale (31%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 30% to 40%.