Shreeji Towers, Wadala East

by Neumec Developer And Builders · Wadala East, Mumbai 400037 · Map

Launched
Sep 20172 yrs 5 mths originally promised
Possession (MahaRERA)
Feb 2021Extended by 1 yr
Concrete structure
100%Nearing possession
Booked
59 of 8470%
Buildings
11 acre
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
27
2 BHK
57
Total units
84
Buildings
1
Land
1 acre
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services88%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 88%Dec 2025: Final finishes 88%Jul 2026: Final finishes 88%Excavation 100%Concrete structure (RCC) 100%Final finishes 88%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%88%59
100%100%88%59
100%100%88%55

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Shreeji Towers by Neumec Developer And Builders is an 84-unit SRA-sanctioned project in Wadala East, Mumbai 400037, launched in September 2017 with possession due in February 2021. 59 units booked out of total 84 units. The concrete structure (RCC) is complete.

Read full summary

Shreeji Towers is an SRA-sanctioned project by Neumec Developer And Builders in Wadala East, Mumbai 400037, registered with MahaRERA as P51900012467. It was launched in September 2017. It has 84 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in February 2021, after an extension of 1 year from the original February 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 88% complete.

59 units booked out of total 84 units (70%).