Mittal Elegant, Chinchbunder

by M M Ideal Infra · Chinchbunder, Mumbai 400009 · Map

Launched
Sep 20172 yrs 3 mths originally promised
Possession (MahaRERA)
Apr 2028Extended by 8 yrs 4 mths
Concrete structure
90%Mid-construction
Booked
–
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
57
Total units
57
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 30%Dec 2025: Final finishes 30%Jul 2026: Final finishes 30%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 90%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%30%–
100%90%30%–
100%90%30%–
100%90%30%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Mittal Elegant by M M Ideal Infra is a 57-unit BMC-sanctioned project in Chinchbunder, Mumbai 400009, launched in September 2017 with possession due in April 2028. The concrete structure (RCC) is 90% complete.

Read full summary

Mittal Elegant is a BMC-sanctioned project by M M Ideal Infra in Chinchbunder, Mumbai 400009, registered with MahaRERA as P51900012877. It was launched in September 2017. It has 57 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2028, extended by 8 years 4 months from the original December 2019. Construction: excavation complete, structure (RCC) 90% complete, final finishes 30% complete.

Since the July 2026 update, the possession date has moved from December 2023 to April 2028.