Dee Jay Square A Wing, Prabhadevi

by Dee Jay Developers · Prabhadevi, Mumbai 400025 · Map

Launched
Sep 20174 yrs 3 mths originally promised
Possession (MahaRERA)
Jul 2027Extended by 5 yrs 7 mths
Concrete structure
90%Mid-construction
Booked (free sale)
1 of 234% · 49 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale1 booked out of 23 units

Rehab49 units for existing members

Total 72 units. Rehab units are not for sale.

Project facts

1 RK
65
Other units
7
Total units
72
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
23
Rehab units
49

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 80%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 90%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%90%1
100%90%80%1
100%90%80%1
100%90%80%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Dee Jay Square A Wing by Dee Jay Developers is a 72-unit BMC-sanctioned project in Prabhadevi, Mumbai 400025, launched in September 2017 with possession due in July 2027. 1 unit booked out of 23 units for sale. The concrete structure (RCC) is 90% complete.

Read full summary

Dee Jay Square A Wing is a BMC-sanctioned project by Dee Jay Developers in Prabhadevi, Mumbai 400025, registered with MahaRERA as P51900013066. It was launched in September 2017. It has 72 units in 1 building: 65 homes (1 RK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 72 units, 23 are for sale and 49 are rehab units for existing members.

Its registered possession date is July 2027, extended by 5 years 7 months from the original December 2021. Construction: excavation complete, structure (RCC) 90% complete, final finishes 90% complete.

1 unit booked out of 23 units for sale (4%).