Safiya Heights, Mandvi

Ready to move

by Smy Associates · Mandvi, Mumbai 400003 · Map

Launched
Nov 20174 yrs 7 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 5 yrs 6 mths
Concrete structure
100%Ready to move
Booked (free sale)
24 of 9625% · 24 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale24 booked out of 96 units

Rehab24 units for existing members

Total 120 units. Rehab units are not for sale.

Project facts

1 BHK
56
2 BHK
1
Other units
63
Total units
120
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
96
Rehab units
24
Reserved units
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 32%Dec 2025: Concrete structure (RCC) 32%Jul 2026: Concrete structure (RCC) 32%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%24
100%32%0%23
100%32%0%–
100%32%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Safiya Heights by Smy Associates is a 120-unit BMC-sanctioned project in Mandvi, Mumbai 400003, launched in November 2017 with possession due in December 2027. 24 units booked out of 96 units for sale. The concrete structure (RCC) is complete.

Read full summary

Safiya Heights is a BMC-sanctioned project by Smy Associates in Mandvi, Mumbai 400003, registered with MahaRERA as P51900014409. It was launched in November 2017. It has 120 units in 1 building: 57 homes (1 and 2 BHK) and 63 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 120 units, 96 are for sale and 24 are rehab units for existing members.

Its registered possession date is December 2027, extended by 5 years 6 months from the original June 2022. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

24 units booked out of 96 units for sale (25%). Since the July 2026 update, 1 more unit has been booked, the reported concrete structure (RCC) has gone from 32% to 100% and the possession date has moved from December 2025 to December 2027.