- Launched
- Nov 20174 yrs 7 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 5 yrs 6 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 24 of 9625% · 24 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale24 booked out of 96 units
Rehab24 units for existing members
Total 120 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 56
- 2 BHK
- 1
- Other units
- 63
- Total units
- 120
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 96
- Rehab units
- 24
- Reserved units
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 24 | |
| 100% | 32% | 0% | 23 | |
| 100% | 32% | 0% | – | |
| 100% | 32% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Safiya Heights by Smy Associates is a 120-unit BMC-sanctioned project in Mandvi, Mumbai 400003, launched in November 2017 with possession due in December 2027. 24 units booked out of 96 units for sale. The concrete structure (RCC) is complete.
Read full summary
Safiya Heights is a BMC-sanctioned project by Smy Associates in Mandvi, Mumbai 400003, registered with MahaRERA as P51900014409. It was launched in November 2017. It has 120 units in 1 building: 57 homes (1 and 2 BHK) and 63 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 120 units, 96 are for sale and 24 are rehab units for existing members.
Its registered possession date is December 2027, extended by 5 years 6 months from the original June 2022. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
24 units booked out of 96 units for sale (25%). Since the July 2026 update, 1 more unit has been booked, the reported concrete structure (RCC) has gone from 32% to 100% and the possession date has moved from December 2025 to December 2027.