Parshwa Lotus & Rangari Heights, Kalachowki
by Gold Plaza Developers Pvt Ltd · Kalachowki, Mumbai 400033 · Map
- Launched
- Dec 20176 yrs originally promised
- Possession (MahaRERA)
- Jan 2027Extended by 3 yrs 1 mth
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 156 of 17191% · 224 rehab units
- Buildings
- 20.5 acres
- MahaRERA complaints
- 23Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale156 booked out of 171 units
Rehab224 units for existing members
Total 395 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 258
- 2 BHK
- 112
- Other units
- 25
- Total units
- 395
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 23
- Free-sale units
- 171
- Rehab units
- 224
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 88% | 156 | |
| 100% | 100% | 80% | 151 | |
| 100% | 83% | 35% | – | |
| 100% | 83% | 35% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Parshwa Lotus & Rangari Heights by Gold Plaza Developers Pvt Ltd is a 395-unit BMC-sanctioned project in Kalachowki, Mumbai 400033, launched in December 2017 with possession due in January 2027. 156 units booked out of 171 units for sale. The concrete structure (RCC) is complete.
Read full summary
Parshwa Lotus & Rangari Heights is a BMC-sanctioned project by Gold Plaza Developers Pvt Ltd in Kalachowki, Mumbai 400033, registered with MahaRERA as P51900014590. It was launched in December 2017. It has 395 units in 2 buildings: 370 homes (1 and 2 BHK) and 25 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 395 units, 171 are for sale and 224 are rehab units for existing members.
Its registered possession date is January 2027, extended by 3 years 1 month from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 88% complete.
156 units booked out of 171 units for sale (91%). Since the July 2026 update, 5 more units have been booked and the possession date has moved from January 2025 to January 2027.