Contemporary Builder Private Limited Tardeo Project, Tardeo
Ready to move
by Contemporary builders private Limited · Tardeo, Mumbai 400034 · Map
- Launched
- Jan 20185 yrs 11 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 4 yrs
- Concrete structure
- 100%Ready to move
- Booked
- –
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 83
- 2 BHK
- 27
- Other units
- 7
- Total units
- 117
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 98% | – | |
| 100% | 100% | 98% | – | |
| 100% | 100% | 98% | 33 |
"–" means MahaRERA shows no figure for that update.
About this project
Contemporary Builder Private Limited Tardeo Project by Contemporary builders private Limited is a 117-unit project in Tardeo, Mumbai 400034, launched in January 2018 with possession due in December 2027. The concrete structure (RCC) is complete.
Read full summary
Contemporary Builder Private Limited Tardeo Project is a project by Contemporary builders private Limited in Tardeo, Mumbai 400034, registered with MahaRERA as P51900014964. It was launched in January 2018. It has 117 units in 2 buildings: 110 homes (1 and 2 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 4 years from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.